PROJECT: Residential New Build
LOCATION: Midland, Texas, USA
PANELS: Greenix Panels GP/W
PROJECT TIMELINE:
Week 1:
- Panels arrived and unloaded
- Installed 1st story walls (including some interior walls for ceiling truss support)
- Installed 2nd story floor
- Installed 2nd story walls
Week 2:
- Crane arrived
- Installed ridge beam and rafters
- Installed Greenix Panel roof of main house
- Installed garage roof (not panels)
- Construction crew completed job
With an construction crew new to building with Greenix Panels, the envelope was completed in 2 weeks.